S.No.
|
Item/Activity
|
Dept./Organisation
|
Time
Limit
|
|
1.
|
(a) Issue of Provisional SSI Regn. Certificate
(b) Issue of Provisional NOC to Medium/Large
Scale Industries of Non-Chemical and Non-Polluting
nature |
Directorate
of Industries & Commerce. |
5days
7 days
|
|
2.
|
Forwarding of common application to the concerned
depts. |
District Industries & Centre |
3
days
|
|
3.
|
Issue of NOC from Pollution angle
|
Pondicherry Pollution Control
Committee
|
6 Weeks
|
|
4.
|
Site
Clearance |
Town
and Country Planning Dept. |
1
Month
|
|
5.
|
Approval
of factory building and machinery lay out |
Inspectorate of Factories and Boilers |
1
Month
|
|
6.
|
Permission
for land use conversion/ground water clearance (outside the Industrial
estate) |
Agriculture
Department |
1
Month
|
|
7.
|
(a)
Power Feasibility certificate.
(b) Energisation of Low Tension connection
on receipt of application
(c) Energisation of High Tension connection
on receipt of application
|
Electricity
Department
Electricity Department
Electricity
Department
|
1
Month
1 Month
3 Months
|
|
8.
|
Clearance under Revenue Acts (if required) |
Revenue
Dept. |
1 month
|
|
9.
|
Publication
of proposals inviting objection, if any in the Official Gazette |
Directorate
of Stationery & Printing |
15
days
|
|
10.
|
Licence, (if required) |
Food
& Drugs Admn. |
1
Month
|
|
11.
|
Licence,(if required) |
Civil
Supplies Dept. |
1
Month
|
|
12.
|
Statutory
permission for establishment of the unit |
Municipality/Commune
Panchayat |
1 month
|